<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
    <SaveVersion>14</SaveVersion>
    <Name>Office Fit-Out (sample)</Name>
    <Title>Office Fit-Out (sample)</Title>
    <ScheduleFromStart>1</ScheduleFromStart>
    <StartDate>2026-03-02T08:00:00</StartDate>
    <FinishDate>2026-05-12T17:00:00</FinishDate>
    <FYStartDate>1</FYStartDate>
    <CriticalSlackLimit>0</CriticalSlackLimit>
    <CurrencyDigits>2</CurrencyDigits>
    <CurrencySymbol>$</CurrencySymbol>
    <CurrencySymbolPosition>0</CurrencySymbolPosition>
    <CalendarUID>1</CalendarUID>
    <DefaultStartTime>08:00:00</DefaultStartTime>
    <MinutesPerDay>480</MinutesPerDay>
    <MinutesPerWeek>2400</MinutesPerWeek>
    <DaysPerMonth>20</DaysPerMonth>
    <DefaultTaskType>0</DefaultTaskType>
    <DefaultFixedCostAccrual>2</DefaultFixedCostAccrual>
    <DurationFormat>7</DurationFormat>
    <WorkFormat>2</WorkFormat>
    <EditableActualCosts>0</EditableActualCosts>
    <HonorConstraints>0</HonorConstraints>
    <EarnedValueMethod>0</EarnedValueMethod>
    <InsertedProjectsLikeSummary>0</InsertedProjectsLikeSummary>
    <MultipleCriticalPaths>0</MultipleCriticalPaths>
    <NewTasksEffortDriven>0</NewTasksEffortDriven>
    <NewTasksEstimated>1</NewTasksEstimated>
    <SplitsInProgressTasks>0</SplitsInProgressTasks>
    <SpreadActualCost>0</SpreadActualCost>
    <SpreadPercentComplete>0</SpreadPercentComplete>
    <TaskUpdatesResource>1</TaskUpdatesResource>
    <FiscalYearStart>0</FiscalYearStart>
    <WeekStartDay>1</WeekStartDay>
    <MoveCompletedEndsBack>0</MoveCompletedEndsBack>
    <MoveRemainingStartsBack>0</MoveRemainingStartsBack>
    <MoveRemainingStartsForward>0</MoveRemainingStartsForward>
    <MoveCompletedEndsForward>0</MoveCompletedEndsForward>
    <BaselineForEarnedValue>0</BaselineForEarnedValue>
    <AutoAddNewResourcesAndTasks>1</AutoAddNewResourcesAndTasks>
    <StatusDate>2026-04-01T17:00:00</StatusDate>
    <CurrentDate>2026-11-05T19:10:30</CurrentDate>
    <MicrosoftProjectServerURL>1</MicrosoftProjectServerURL>
    <Autolink>1</Autolink>
    <NewTaskStartDate>0</NewTaskStartDate>
    <NewTasksAreManual>1</NewTasksAreManual>
    <DefaultTaskEVMethod>0</DefaultTaskEVMethod>
    <ProjectExternallyEdited>0</ProjectExternallyEdited>
    <ActualsInSync>0</ActualsInSync>
    <RemoveFileProperties>0</RemoveFileProperties>
    <AdminProject>0</AdminProject>
    <ExtendedAttributes/>
    <Calendars>
        <Calendar>
            <UID>1</UID>
            <Name>Standard</Name>
            <IsBaseCalendar>1</IsBaseCalendar>
            <IsBaselineCalendar>0</IsBaselineCalendar>
            <BaseCalendarUID>-1</BaseCalendarUID>
            <WeekDays>
                <WeekDay>
                    <DayType>1</DayType>
                    <DayWorking>0</DayWorking>
                </WeekDay>
                <WeekDay>
                    <DayType>2</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>3</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>4</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>5</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>6</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>7</DayType>
                    <DayWorking>0</DayWorking>
                </WeekDay>
            </WeekDays>
        </Calendar>
    </Calendars>
    <Tasks>
        <Task>
            <UID>1</UID>
            <ID>1</ID>
            <Name>Design</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>1</WBS>
            <OutlineNumber>1</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-02T08:00:00</Start>
            <Finish>2026-03-11T17:00:00</Finish>
            <Duration>PT64H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>1</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
        </Task>
        <Task>
            <UID>2</UID>
            <ID>2</ID>
            <Name>Site survey</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>1.1</WBS>
            <OutlineNumber>1.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-02T08:00:00</Start>
            <Finish>2026-03-04T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-02T08:00:00</ActualStart>
            <ActualFinish>2026-03-04T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-02T08:00:00</Start>
                <Finish>2026-03-04T17:00:00</Finish>
                <Duration>PT24H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>3</UID>
            <ID>3</ID>
            <Name>Space plan</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>1.2</WBS>
            <OutlineNumber>1.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-05T08:00:00</Start>
            <Finish>2026-03-11T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-05T08:00:00</ActualStart>
            <ActualFinish>2026-03-11T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-05T08:00:00</Start>
                <Finish>2026-03-11T17:00:00</Finish>
                <Duration>PT40H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>4</UID>
            <ID>4</ID>
            <Name>Client sign-off</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>1.3</WBS>
            <OutlineNumber>1.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-11T17:00:00</Start>
            <Finish>2026-03-11T17:00:00</Finish>
            <Duration>PT0H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>1</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-11T17:00:00</ActualStart>
            <ActualFinish>2026-03-11T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-11T17:00:00</Start>
                <Finish>2026-03-11T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>5</UID>
            <ID>5</ID>
            <Name>Permits</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>2</WBS>
            <OutlineNumber>2</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-03-31T17:00:00</Finish>
            <Duration>PT112H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>1</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
        </Task>
        <Task>
            <UID>6</UID>
            <ID>6</ID>
            <Name>Prepare permit drawings</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>2.1</WBS>
            <OutlineNumber>2.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-03-17T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-12T08:00:00</ActualStart>
            <ActualFinish>2026-03-17T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-12T08:00:00</Start>
                <Finish>2026-03-17T17:00:00</Finish>
                <Duration>PT32H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>7</UID>
            <ID>7</ID>
            <Name>Building permit review</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>2.2</WBS>
            <OutlineNumber>2.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-18T08:00:00</Start>
            <Finish>2026-03-31T17:00:00</Finish>
            <Duration>PT80H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-18T08:00:00</ActualStart>
            <ActualFinish>2026-03-31T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes>City review took two days longer than planned. The permit was issued with no conditions.</Notes>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>6</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-18T08:00:00</Start>
                <Finish>2026-03-27T17:00:00</Finish>
                <Duration>PT64H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>8</UID>
            <ID>8</ID>
            <Name>Permit issued</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>2.3</WBS>
            <OutlineNumber>2.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-31T17:00:00</Start>
            <Finish>2026-03-31T17:00:00</Finish>
            <Duration>PT0H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>1</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-31T17:00:00</ActualStart>
            <ActualFinish>2026-03-31T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>7</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-27T17:00:00</Start>
                <Finish>2026-03-27T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>9</UID>
            <ID>9</ID>
            <Name>Procurement</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3</WBS>
            <OutlineNumber>3</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-04-17T17:00:00</Finish>
            <Duration>PT216H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>1</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>70</PercentComplete>
            <RemainingDuration>PT64H48M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
        </Task>
        <Task>
            <UID>10</UID>
            <ID>10</ID>
            <Name>Order furniture</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3.1</WBS>
            <OutlineNumber>3.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-03-13T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-12T08:00:00</ActualStart>
            <ActualFinish>2026-03-13T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-12T08:00:00</Start>
                <Finish>2026-03-13T17:00:00</Finish>
                <Duration>PT16H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>11</UID>
            <ID>11</ID>
            <Name>Furniture lead time</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3.2</WBS>
            <OutlineNumber>3.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-16T08:00:00</Start>
            <Finish>2026-04-17T17:00:00</Finish>
            <Duration>PT200H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>52</PercentComplete>
            <ActualStart>2026-03-16T08:00:00</ActualStart>
            <RemainingDuration>PT96H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-16T08:00:00</Start>
                <Finish>2026-04-17T17:00:00</Finish>
                <Duration>PT200H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>12</UID>
            <ID>12</ID>
            <Name>Order lighting</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3.3</WBS>
            <OutlineNumber>3.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-03-12T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-12T08:00:00</ActualStart>
            <ActualFinish>2026-03-12T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-12T08:00:00</Start>
                <Finish>2026-03-12T17:00:00</Finish>
                <Duration>PT8H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>13</UID>
            <ID>13</ID>
            <Name>Lighting lead time</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3.4</WBS>
            <OutlineNumber>3.4</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-03-13T08:00:00</Start>
            <Finish>2026-03-30T17:00:00</Finish>
            <Duration>PT96H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <ActualStart>2026-03-13T08:00:00</ActualStart>
            <ActualFinish>2026-03-30T17:00:00</ActualFinish>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>12</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-13T08:00:00</Start>
                <Finish>2026-03-30T17:00:00</Finish>
                <Duration>PT96H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>14</UID>
            <ID>14</ID>
            <Name>Construction</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4</WBS>
            <OutlineNumber>4</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-01T08:00:00</Start>
            <Finish>2026-05-05T17:00:00</Finish>
            <Duration>PT200H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>1</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>4</PercentComplete>
            <RemainingDuration>PT192H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
        </Task>
        <Task>
            <UID>15</UID>
            <ID>15</ID>
            <Name>Strip out</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.1</WBS>
            <OutlineNumber>4.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-01T08:00:00</Start>
            <Finish>2026-04-03T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>33</PercentComplete>
            <ActualStart>2026-04-01T08:00:00</ActualStart>
            <RemainingDuration>PT16H4M48S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>8</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-03-30T08:00:00</Start>
                <Finish>2026-04-01T17:00:00</Finish>
                <Duration>PT24H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>16</UID>
            <ID>16</ID>
            <Name>Partition walls</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.2</WBS>
            <OutlineNumber>4.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-06T08:00:00</Start>
            <Finish>2026-04-13T17:00:00</Finish>
            <Duration>PT48H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT48H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>15</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-04-02T08:00:00</Start>
                <Finish>2026-04-09T17:00:00</Finish>
                <Duration>PT48H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>17</UID>
            <ID>17</ID>
            <Name>Electrical first fix</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.3</WBS>
            <OutlineNumber>4.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-14T08:00:00</Start>
            <Finish>2026-04-17T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>16</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-04-10T08:00:00</Start>
                <Finish>2026-04-15T17:00:00</Finish>
                <Duration>PT32H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>18</UID>
            <ID>18</ID>
            <Name>Install lighting</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.4</WBS>
            <OutlineNumber>4.4</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-20T08:00:00</Start>
            <Finish>2026-04-22T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>17</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>13</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-04-16T08:00:00</Start>
                <Finish>2026-04-20T17:00:00</Finish>
                <Duration>PT24H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>19</UID>
            <ID>19</ID>
            <Name>Paint and finishes</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.5</WBS>
            <OutlineNumber>4.5</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-23T08:00:00</Start>
            <Finish>2026-04-29T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>18</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-04-21T08:00:00</Start>
                <Finish>2026-04-27T17:00:00</Finish>
                <Duration>PT40H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>20</UID>
            <ID>20</ID>
            <Name>Flooring</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4.6</WBS>
            <OutlineNumber>4.6</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-04-30T08:00:00</Start>
            <Finish>2026-05-05T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>19</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-04-28T08:00:00</Start>
                <Finish>2026-05-01T17:00:00</Finish>
                <Duration>PT32H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>21</UID>
            <ID>21</ID>
            <Name>Handover</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>5</WBS>
            <OutlineNumber>5</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-05-06T08:00:00</Start>
            <Finish>2026-05-12T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>1</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
        </Task>
        <Task>
            <UID>22</UID>
            <ID>22</ID>
            <Name>Furniture install</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>5.1</WBS>
            <OutlineNumber>5.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-05-06T08:00:00</Start>
            <Finish>2026-05-08T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>20</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>11</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-05-04T08:00:00</Start>
                <Finish>2026-05-06T17:00:00</Finish>
                <Duration>PT24H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>23</UID>
            <ID>23</ID>
            <Name>Snag list</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>5.2</WBS>
            <OutlineNumber>5.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-05-11T08:00:00</Start>
            <Finish>2026-05-12T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>22</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-05-07T08:00:00</Start>
                <Finish>2026-05-08T17:00:00</Finish>
                <Duration>PT16H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
            </Baseline>
        </Task>
        <Task>
            <UID>24</UID>
            <ID>24</ID>
            <Name>Handover to client</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>5.3</WBS>
            <OutlineNumber>5.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2026-05-12T17:00:00</Start>
            <Finish>2026-05-12T17:00:00</Finish>
            <Duration>PT0H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>1</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>23</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2026-05-08T17:00:00</Start>
                <Finish>2026-05-08T17:00:00</Finish>
            </Baseline>
        </Task>
    </Tasks>
    <Resources>
        <Resource>
            <UID>1</UID>
            <ID>1</ID>
            <Name>Dana Ortiz</Name>
            <Type>1</Type>
            <IsNull>0</IsNull>
            <Initials>DO</Initials>
            <MaxUnits>1</MaxUnits>
            <PeakUnits>1</PeakUnits>
            <OverAllocated>0</OverAllocated>
            <Start>2026-03-02T08:00:00</Start>
            <Finish>2026-05-12T17:00:00</Finish>
            <CanLevel>0</CanLevel>
            <StandardRateFormat>2</StandardRateFormat>
            <OvertimeRateFormat>2</OvertimeRateFormat>
            <IsGeneric>0</IsGeneric>
            <IsInactive>0</IsInactive>
            <IsEnterprise>0</IsEnterprise>
            <IsBudget>0</IsBudget>
        </Resource>
        <Resource>
            <UID>2</UID>
            <ID>2</ID>
            <Name>Sam Lee</Name>
            <Type>1</Type>
            <IsNull>0</IsNull>
            <Initials>SL</Initials>
            <MaxUnits>1</MaxUnits>
            <PeakUnits>1</PeakUnits>
            <OverAllocated>0</OverAllocated>
            <Start>2026-03-12T08:00:00</Start>
            <Finish>2026-05-08T17:00:00</Finish>
            <CanLevel>0</CanLevel>
            <StandardRateFormat>2</StandardRateFormat>
            <OvertimeRateFormat>2</OvertimeRateFormat>
            <IsGeneric>0</IsGeneric>
            <IsInactive>0</IsInactive>
            <IsEnterprise>0</IsEnterprise>
            <IsBudget>0</IsBudget>
        </Resource>
        <Resource>
            <UID>3</UID>
            <ID>3</ID>
            <Name>Build crew</Name>
            <Type>1</Type>
            <IsNull>0</IsNull>
            <Initials>Bc</Initials>
            <MaxUnits>1</MaxUnits>
            <PeakUnits>1</PeakUnits>
            <OverAllocated>0</OverAllocated>
            <Start>2026-04-01T08:00:00</Start>
            <Finish>2026-05-08T17:00:00</Finish>
            <CanLevel>0</CanLevel>
            <StandardRateFormat>2</StandardRateFormat>
            <OvertimeRateFormat>2</OvertimeRateFormat>
            <IsGeneric>0</IsGeneric>
            <IsInactive>0</IsInactive>
            <IsEnterprise>0</IsEnterprise>
            <IsBudget>0</IsBudget>
        </Resource>
        <Resource>
            <UID>4</UID>
            <ID>4</ID>
            <Name>Electrician</Name>
            <Type>1</Type>
            <IsNull>0</IsNull>
            <Initials>E</Initials>
            <MaxUnits>1</MaxUnits>
            <PeakUnits>1</PeakUnits>
            <OverAllocated>0</OverAllocated>
            <Start>2026-04-14T08:00:00</Start>
            <Finish>2026-04-22T17:00:00</Finish>
            <CanLevel>0</CanLevel>
            <StandardRateFormat>2</StandardRateFormat>
            <OvertimeRateFormat>2</OvertimeRateFormat>
            <IsGeneric>0</IsGeneric>
            <IsInactive>0</IsInactive>
            <IsEnterprise>0</IsEnterprise>
            <IsBudget>0</IsBudget>
        </Resource>
    </Resources>
    <Assignments>
        <Assignment>
            <UID>1</UID>
            <TaskUID>2</TaskUID>
            <ResourceUID>1</ResourceUID>
            <ActualFinish>2026-03-04T17:00:00</ActualFinish>
            <Finish>2026-03-04T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT24H0M0S</RemainingWork>
            <Start>2026-03-02T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>2</UID>
            <TaskUID>3</TaskUID>
            <ResourceUID>1</ResourceUID>
            <ActualFinish>2026-03-11T17:00:00</ActualFinish>
            <Finish>2026-03-11T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT40H0M0S</RemainingWork>
            <Start>2026-03-05T08:00:00</Start>
            <Units>1</Units>
            <Work>PT40H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>3</UID>
            <TaskUID>6</TaskUID>
            <ResourceUID>1</ResourceUID>
            <ActualFinish>2026-03-17T17:00:00</ActualFinish>
            <Finish>2026-03-17T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT32H0M0S</RemainingWork>
            <Start>2026-03-12T08:00:00</Start>
            <Units>1</Units>
            <Work>PT32H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>4</UID>
            <TaskUID>10</TaskUID>
            <ResourceUID>2</ResourceUID>
            <ActualFinish>2026-03-13T17:00:00</ActualFinish>
            <Finish>2026-03-13T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT16H0M0S</RemainingWork>
            <Start>2026-03-12T08:00:00</Start>
            <Units>1</Units>
            <Work>PT16H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>5</UID>
            <TaskUID>12</TaskUID>
            <ResourceUID>2</ResourceUID>
            <ActualFinish>2026-03-12T17:00:00</ActualFinish>
            <Finish>2026-03-12T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT8H0M0S</RemainingWork>
            <Start>2026-03-12T08:00:00</Start>
            <Units>1</Units>
            <Work>PT8H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>6</UID>
            <TaskUID>15</TaskUID>
            <ResourceUID>3</ResourceUID>
            <Finish>2026-04-03T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT24H0M0S</RemainingWork>
            <Start>2026-04-01T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>7</UID>
            <TaskUID>16</TaskUID>
            <ResourceUID>3</ResourceUID>
            <Finish>2026-04-13T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT48H0M0S</RemainingWork>
            <Start>2026-04-06T08:00:00</Start>
            <Units>1</Units>
            <Work>PT48H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>8</UID>
            <TaskUID>17</TaskUID>
            <ResourceUID>4</ResourceUID>
            <Finish>2026-04-17T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT32H0M0S</RemainingWork>
            <Start>2026-04-14T08:00:00</Start>
            <Units>1</Units>
            <Work>PT32H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>9</UID>
            <TaskUID>18</TaskUID>
            <ResourceUID>4</ResourceUID>
            <Finish>2026-04-22T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT24H0M0S</RemainingWork>
            <Start>2026-04-20T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>10</UID>
            <TaskUID>19</TaskUID>
            <ResourceUID>3</ResourceUID>
            <Finish>2026-04-29T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT40H0M0S</RemainingWork>
            <Start>2026-04-23T08:00:00</Start>
            <Units>1</Units>
            <Work>PT40H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>11</UID>
            <TaskUID>20</TaskUID>
            <ResourceUID>3</ResourceUID>
            <Finish>2026-05-05T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT32H0M0S</RemainingWork>
            <Start>2026-04-30T08:00:00</Start>
            <Units>1</Units>
            <Work>PT32H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>12</UID>
            <TaskUID>22</TaskUID>
            <ResourceUID>2</ResourceUID>
            <Finish>2026-05-08T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT24H0M0S</RemainingWork>
            <Start>2026-05-06T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>13</UID>
            <TaskUID>22</TaskUID>
            <ResourceUID>3</ResourceUID>
            <Finish>2026-05-08T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT24H0M0S</RemainingWork>
            <Start>2026-05-06T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>14</UID>
            <TaskUID>23</TaskUID>
            <ResourceUID>1</ResourceUID>
            <Finish>2026-05-12T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT16H0M0S</RemainingWork>
            <Start>2026-05-11T08:00:00</Start>
            <Units>1</Units>
            <Work>PT16H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>15</UID>
            <TaskUID>1</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualWork>PT64H0M0S</ActualWork>
            <Finish>2026-03-11T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-02T08:00:00</Start>
            <Units>1</Units>
            <Work>PT64H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>16</UID>
            <TaskUID>4</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <ActualFinish>2026-03-11T17:00:00</ActualFinish>
            <Finish>2026-03-11T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-11T17:00:00</Start>
            <Units>1</Units>
        </Assignment>
        <Assignment>
            <UID>17</UID>
            <TaskUID>5</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualWork>PT112H0M0S</ActualWork>
            <Finish>2026-03-31T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-12T08:00:00</Start>
            <Units>1</Units>
            <Work>PT112H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>18</UID>
            <TaskUID>7</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualFinish>2026-03-31T17:00:00</ActualFinish>
            <ActualWork>PT80H0M0S</ActualWork>
            <Finish>2026-03-31T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-18T08:00:00</Start>
            <Units>1</Units>
            <Work>PT80H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>19</UID>
            <TaskUID>8</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <ActualFinish>2026-03-31T17:00:00</ActualFinish>
            <Finish>2026-03-31T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-31T17:00:00</Start>
            <Units>1</Units>
        </Assignment>
        <Assignment>
            <UID>20</UID>
            <TaskUID>9</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>70</PercentWorkComplete>
            <ActualWork>PT151H12M0S</ActualWork>
            <Finish>2026-04-17T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT64H48M0S</RemainingWork>
            <Start>2026-03-12T08:00:00</Start>
            <Units>1</Units>
            <Work>PT216H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>21</UID>
            <TaskUID>11</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>52</PercentWorkComplete>
            <ActualWork>PT104H0M0S</ActualWork>
            <Finish>2026-04-17T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT96H0M0S</RemainingWork>
            <Start>2026-03-16T08:00:00</Start>
            <Units>1</Units>
            <Work>PT200H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>22</UID>
            <TaskUID>13</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualFinish>2026-03-30T17:00:00</ActualFinish>
            <ActualWork>PT96H0M0S</ActualWork>
            <Finish>2026-03-30T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2026-03-13T08:00:00</Start>
            <Units>1</Units>
            <Work>PT96H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>23</UID>
            <TaskUID>14</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>4</PercentWorkComplete>
            <ActualWork>PT8H0M0S</ActualWork>
            <Finish>2026-05-05T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT192H0M0S</RemainingWork>
            <Start>2026-04-01T08:00:00</Start>
            <Units>1</Units>
            <Work>PT200H0M0S</Work>
        </Assignment>
    </Assignments>
</Project>